Resolution No. 2022-56 Work Authorization for Yacht Club Drive Seawall Hardening Improvements Project - Kimley-Horn and Associates, Inc. - September 13, 2022 CITY OF AVENTURA RESOLUTION NO. 2022-56
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF
AVENTURA, FLORIDA, AUTHORIZING THE CITY MANAGER TO
EXECUTE THE ATTACHED WORK AUTHORIZATION NO. 2022-
043508136-001 IN THE AMOUNT OF $175,491.50 FOR PROFESSIONAL
DESIGN SERVICES FOR THE YACHT CLUB DRIVE SEAWALL
HARDENING IMPROVEMENTS PROJECT BY AND BETWEEN THE
CITY OF AVENTURA AND KIMLEY-HORN & ASSOCIATES, INC.;
PROVIDING FOR IMPLEMENTATION; AND PROVIDING FOR AN
EFFECTIVE DATE.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF AVENTURA, FLORIDA:
Section 1. That the City Manager is hereby authorized to execute the attached
Work Authorization No. 2022-043508136-001 ($175,491 .50) for professional design
services by and between the City of Aventura and Kimley-Horn & Associates, Inc.
Section 2. That the City Manager is authorized to do all things necessary to
carry out the aims of this Resolution.
Section 3. This Resolution shall become effective immediately upon its
adoption.
The foregoing Resolution was offered by Commissioner Narotsky, who moved its
adoption. The motion was seconded by Commissioner Joel, and upon being put to a vote,
the vote was as follows:
Commissioner Rachel S. Friedland Absent
Commissioner Billy Joel Yes
Commissioner Dr. Linda Marks Yes
Commissioner Marc Narotsky Yes
Commissioner Robert Shelley Absent
Vice Mayor Denise Landman Yes
Mayor Enid Weisman Yes
City of Aventura Resolution No. 2022-56
PASSED AND ADOPTED this 13t" day of September, 2022.
•
ENID WEISMAN, MAYOR
ATTEST:
ELLISA L. HORVAT , MMC
CITY CLERK
APPROVED AS TO LEGAL SUFFICIENCY:
CITY ATTORNEY
Page 2 of 2
WORK AUTHORIZATION NO. 2022-043508136-001
2022 YACHT CLUB DRIVE SEAWALL REPAIR
The City of Aventura has requested Work Authorization No. 2022-043508136-001 as provided
for in the Agreement between the City of Aventura and Kimley-Horn and Associates, Inc. and
approved by the City Commission on July 9, 2019.
This Work Authorization No. 2022-043508136-001 provides for technical services in accordance
with Articles 3, 4, 6, 7 and 8 of the Agreement as further detailed in the scope of services
Exhibit A.
Payment for such services shall be in accordance with Article 5 of the Agreement.
Review Phase
Site Visit $4,483.00
Review of Existing Documentation $3,356.00
Total Review Phase—Lump Sum $7,839.00
Design Phase
Survey $21,825.00
Geotech $28,127.50
Construction Documents $37,558.00
Total Design Phase— Lump Sum $87,510.50
Permitting Phase
Environmental Permitting $15,668.00
Total Permitting Phase—Lump Sum $15,668.00
Bidding Phase
Limited Bidding Assistance $7,618.00
Total Bidding Phase—Lump Sum $7,618.00
Construction Phase
Shop Drawing and RFI Review $7,520.00
Construction Meetings $16,780.00
Site Visits $30,900.00
Pay App Review $1,656.00
Total Construction Phase—Lump Sum $56,856.00
Total Lump Sum Labor Fee $175,491.50
The time period for this work authorization will be:
Design Phase..............................................................60 Days
Permitting phase (estimate)...................................120 Days
Bidding Phase............................................................45 Days
Construction Phase (estimate) ...............................120 Days (after material acquisition)
CITY:
CITY OF AVENTURA, FLORIDA
through its City Manager
BY
City Manager
Ronald J. Wasson
day of 12022
Notice to Proceed Yes No
Project Initiation Date
RECOMMENDED through its
Director of Public Works Transportation
BY
Capital Projects Manager
Antonio F. Tomei
day of , 2022
Exhibit A
Project Description
The services to be provided under this proposal is to prepare construction documents to repair
the seawall located along the north side of Yacht Club Drive for approximately 1,500 LF of wall.
The total length of seawall in this area is approximately 1,900 LF, however approximately 400 LF
had been previously repaired under an emergency project due to a partial collapse. Figure 1
below shows the limits of the seawall. The project will include the installation of new battered
piles in front of the existing seawall to stabilize and increase the service life of the seawall. As
part of this project, a surveyor and geotechnical engineer will be engaged as subconsultants to
obtain on-site data for the design of the wall.
r _1-..
1 �• .! qr �y'�T� 1
Assumed Project Limits
i _7 ` 7.
Figure 1: Limits of Seawall (Source: Google Earth) [Red line shows limits of seawall]
Scope of Services
The professional services for this project will include the following:
Task 1—Site Visit and Existing Document Review
Kimley-Horn will conduct a site visit is to document and quantify the structural repairs required
throughout the length of the seawall for the development of the repair plans. The site visit will
be performed by two (2) engineering professionals, including one licensed PE in Florida. Prior to
the site visit, Kimley-Horn will review the readily available prior reports, plans, and as-built
documents (to be provided by the City) and develop a preliminary seawall layout to be used for
field notes.
As part of this visit, SCUBA equipment may be used to understand the condition of the wall
elements (piles and wall panels) near the mudline and the splash zone. Photographs taken may
be used as part of Task 2 to illustrate the repairs to the seawall.
Upon completion of the site visit, Kimley-Horn will schedule a conference call with the City to
review our field observations and to discuss the overall repair items that should be addressed in
the repair plans. Meeting minutes will be issued by Kimley-Horn.
The City of Aventura shall provide the following information prior to scheduling the site visit:
• Record Drawings, if any
• Maintenance Records, if any
• Prior Seawall Evaluation Reports
• Recent repair plans and geotechnical data from emergency repair
• Coordination with the cathodic protection installer
• Prior permits
Task 2—Seawall Repair Drawings, Calculations, and Specifications
The purpose of this Task is to prepare engineering plans depicting the seawall repairs along the
north side of Yacht Club Drive in Aventura, Florida.
The Consultant will engage the services of both a Geotechnical Engineering and a Surveying
subconsultant. The Geotechnical Engineering firm will obtain three (3) borings approximately
50 feet in depth with one (1) boring being in the water.The Geotechnical Engineer will provide
soil parameters and information related to the design of the retrofit. Additionally, the
Consultant will utilize high resolution aerials in the development of construction drawings
supplemented by a site specific topographic and bathymetric survey to be obtained from the
Surveying firm as part of this task. The survey scope will include locating upland features as well
as inlet, pipes, penetrations and outfalls through the existing seawall.
The Consultant will perform engineering and design services for the preparation of construction
plans and design requirements to stabilize the seawall and repair specific deficiencies as
discussed during the meeting under Task 1.
The deliverable shall consist of engineering plans for the seawall improvements. Construction
plans will be prepared to a level suitable for a competitive bidding process in conformance with
the current Florida Building Code (2020). The set of plans is anticipated to include the following
sheets:
• Cover Sheet
• General Notes and Technical Specifications
• Notes and details for erosion and sediment control measures.
• Plan and elevation sheets with work identification sheets
• Annotated photographs of specific repairs
• Typical section and sequence of construction details
• Detail Sheets
Project assumptions:
• No guardrail/barrier will be installed on top of the wall.
• The wall (top of cap) elevation will match existing.
• The existing cathodic protection on the existing cap is assumed to be removed
and re-installed by the original installer under a separate contract directly with
the City.
• Specifications will be included in the plans in the form of general notes. (A
project manual/specification package is assumed to not be included as part of
this task).
During this task, Kimley-Horn will attend up to two (2) coordination meetings with the City to
discuss project requirements. Meetings are assumed to be virtual and last no more than one (1)
hour.
Kimley-Horn will submit 60% progress set(11"x17")to the Client for review and comments. Upon
submittal of the 60% plans, Kimley-Horn will attend one virtual meeting with the Client to answer
any comments/questions on the progress set.
Kimley-Horn will submit two (2) half-size (11"x17") printed copies of the final design plans and
construction cost estimate to the City staff for bid and construction.The final plans will be signed
and sealed by a licensed Florida Engineer. All deliverables shall also be submitted in PDF format.
Task 3—Environmental —Seagrass Survey and Permitting
This proposal assumes that the seawall replacement project will require environmental
regulatory permits from the Florida Department of Environmental Protection (FDEP) and Miami-
Dade County Division of Environmental Resources Management (DERM).
This proposal assumes that the existing seawall was either constructed in conformance with
permits issued by USACE, FDEP and DERM, or was constructed prior to establishment of related
permitting requirements.
This proposal is based on the assumption that the improvements will be installed either directly
landward of the existing seawall, or directly waterward of the existing seawall, such that the face
of the new seawall is within 18 inches of the face of the existing seawall.
This proposal assumes that the project will qualify for permitting as a State Programmatic
General Permit (SPGP) issued by FDEP on behalf of the USACE; and a Class I Short Form Permit
with DERM. It is possible that DERM will require installation of new riprap at a 2:1 slope,
extending a maximum of eight feet from the face of the reconstructed seawall. If rip-rap is
required, the SPGP only allows for 100 linear feet and therefore, separate authorizations would
be required for the rip-rap. If rip-rap is required, a separate scope and fee will be prepared for
the additional permitting efforts needed.
This proposal assumes that all application fees shall be paid by the Client.
Task 3.1— Environmental Regulatory Permitting (State/Federal)
Kimley-Horn will coordinate and attend one pre-application meeting with FDEP to discuss existing
conditions and permitting requirements. Kimley-Horn will prepare a State Programmatic General
Permit for submittal to FDEP, to include figures illustrating existing and proposed conditions.
Application fees will be paid by the Client.
Following application submittal, Kimley-Horn will respond to one Request for Available
Information (RAI) from FDEP. Any additional RAIs or meetings will be considered additional
services.
It is assumed that the contractor will follow the Standard Manatee Conditions for In-Water Work
(2011) in order to prevent impacts to the West Indian manatee and will implement a standard
turbidity control plan to assure water quality during seawall improvement construction.
Task 3.2— Environmental Regulatory Permitting (County)
For the DERM Class I Short Form Permit, Kimley-Horn will attend one pre-application meeting
with Miami-Dade County. Kimley-Horn will prepare an application for improvements to the
seawall and a Class I (Short Form) Approval from DERM. It is anticipated that application
materials will encompass essentially the same information submitted to FDEP. Kimley-Horn will
submit the application package to DERM. The DERM permit fee will be determined based on
estimated construction cost and will be paid by the Client.
Following application submittal, Kimley-Horn will respond to one RAI from DERM. Any additional
RAIs or meetings will be considered additional services.
Task 4— Limited Bidding Assistance
It is our understanding that the City will use a competitive bidding process to award the contact
to a qualified contractor to construct the improvements. Kimley-Horn shall assist the City during
the bidding process by attending one (1) pre-bid meeting and issuing up to two (2) addenda in
response to interested contractor questions or requests for information during the bid process.
All responses by Kimley-Horn will be approved by the City prior to issuance. Once bids are
received, Kimley-Horn shall review the bids and provide a recommendation to the City of the
apparent low bidder's price proposal. The City will be responsible for making the award and
notifying the successful bidder.
Task 5—Construction Phase Services
As the Engineer of Record, the Consultant will provide limited construction phase services to
assist the City in providing plan clarifications as well as responding to requests for information
(RFI's) during the construction of the project. The scope for his task is based on the assumed
construction duration of 120 days.
During the construction startup phase, it is assumed that at most three (3) requests for
information will be received and reviewed. Additionally, the Consultant will review the
provided shop drawings (up to a maximum of five (5)) for general compliance with the intent of
the design.
Kimley-horn will also lead weekly construction meetings (up to sixteen (16) meetings) and
prepare meeting minutes. It is assumed that most construction meetings will be held virtually
and up to four (4) meetings will be held in the field concurrent with the weekly site visits.
Meetings are anticipated to last no more than 1-hour. It is assumed that the Consultant will
perform weekly site visits to the project to document and observe the construction. It is
assumed that sixteen (16) site visits will be performed throughout the duration of the project.
These weekly site visits are anticipated to be at most four (4) hours on site and field
observation reports will be provided as part of each site visit. An additional six (6) site visits, in
excess of the scheduled weekly site visits, are anticipated to be required during critical aspects
of construction.The services provided in this Task are expected to be sufficient for the
Consultant to certify the project to the City of Aventura upon completion of construction. It is
assumed the Consultant will review and approve Pay Applications from the Contractor at the
end of each month. A total of four (4) Pay Applications are assumed to be included in the scope
of work.